Announcements

If you have any concerns or questions about any disruption or shutdown notices, please contact the Facilities Management Service Desk at 613-727-4723 ext. 7710 Monday to Friday, between 7:30 a.m. and 4:00 p.m. or via email at 7710@algonquincollege.com


Notice of Construction Activity – P Lighting Project

Facilities Management will commence lighting maintenance work in Building P during the mid semester break (Oct 26-30).

During this time, lighting in various areas of Building P will be temporarily turned off and restored as work progresses. Occupants may experience intermittent lighting interruptions throughout the day while contractors complete the required maintenance.

As part of this activity, there may be minor disruptions in the affected areas. Facilities Management will work closely with the contractor to minimize inconvenience and ensure the work is completed safely and efficiently.

We sincerely appreciate your patience and understanding as we complete this important work. Thank you for your cooperation as we continue to enhance and maintain our campus facilities.


Air Balancing – C/J Bridge and J/D Link – Oct. 26, 2026

At approximately 8 a.m. on Oct. 26, 2026, we will be conducting an air pressure test on the C/J Bridge as well as the J/D Link. Each test will take about five minutes where we will not be able to open the doors on either side of these throughways.

Hoping that there is very minimal traffic at 8 a.m. on Oct. 26, 2026, however, we would like some sort of record in the event we need to refer to it during that time.


Domestic Water Shutdown – Oct. 31, 2026

Please be advised that on Saturday, October 31, 2026, from 7:00 a.m. to 5:00 p.m., all domestic cold and hot water services will be shut down to the following buildings to facilitate critical valve replacements within the College’s main domestic water infrastructure:

  • Building A
  • Building B
  • Building C
  • DARE District
  • New STEM Labs (Building A)

During this outage, all plumbing fixtures will be out of service, including sinks, toilets, showers, and other water-dependent equipment. We kindly ask that occupants refrain from using any plumbing fixtures during the shutdown period.

These repairs are necessary to improve the reliability of the domestic water distribution system and to reduce the risk of future service disruptions.

We apologize for any inconvenience this may cause and thank you in advance for your patience, cooperation, and understanding while this critical work is completed.


Notice of Construction Activity – Building T Vestibule Refurbishment Project

Facilities Management in coordination with the assigned contractor, will commence work on the Building T Vestibule Refurbishment Project on Monday, October 5, 2026. The work is expected to continue for approximately three months.

Work will begin with Vestibules 1 and 2 and will then progress to the remaining vestibules shaded on the floor plan below.

The building will remain accessible throughout the project; however, temporary access restrictions may occur at individual vestibules while work is underway. Where required, occupants will be directed to an alternate vestibule. We appreciate your cooperation and understanding during the construction period.

We will work closely with the contractor to minimize disruption as much as possible.

Building T vestibule Refurbishment Project

Notice of Construction Activities – P111 and P124

Start Date: Monday, June 15, 2026

Please be advised that construction activities will commence in Rooms P111 and P124 starting Monday, June 15, 2026, and will continue until further notice.

Scope of Work: The project includes demolition of existing floor slabs and associated renovation activities within both locations.

After-Hours Demolition Work: To minimize disruption to building operations, slab demolition activities will be performed after hours, beginning at 9:00 p.m. and continuing overnight until the early morning.

Hoarding and Site Logistics

  • The demolition area within P124 will be fully hoarded and secured as shown in the attached schedule and site plan.
  • A temporary construction waste bin will be located outside the work areas, as indicated on the attached sketch.

Impact on Building Operations

  • Demolition activities are scheduled after hours and are not expected to impact regular building operations.
  • During regular operating hours, construction activities will continue within P111. This area will remain closed and inaccessible to students, staff, and visitors for the duration of the work.
  • All reasonable measures will be taken to minimize noise, dust, and disruption while maintaining a safe environment for building occupants.

We appreciate your patience and understanding as we complete these improvements.

Paramedic Boxes - Site Layout Plan - 12.06.26_Page_1 Paramedic Boxes - Site Layout Plan - 12.06.26_Page_2